CIPTA BANGUN NUSANTARA MONTHLY UPDATE

01 Maret 2023

CIPTA BANGUN NUSANTARA MARCH 2023 UPDATE REPORT

 

Monthly Project & Construction Activities Reports

No. Project / Construction Activities Location Client Status
1

Construction for Salak Make Up Well 2023 

Gn. Salak    

SEGS

Project Start-Up 
2

Geohazard Mitigation Program for Darajat and Wayang Windu Star Energy Geothermal

Darajat, Wayang Windu Pengalengan 

SEGD, SEGWW 

On Going
3

EPC New Fire Water System Project 

Bontang

 PKT

On Going 
4

Infrastructures and Drilling Support Facilities Well Pad WJR-1N 

Sarulla  

SOL

Finishing 
5

Mechanical & Civil Construction Service for WIP 2022 Wayang Windu 

Wayang Windu, Pengalengan 

SEGWWL 

On Going
6

AWI 18 Brine Line System Modification Project 

Gn. Salak

SEGS

On Going

Brine Transfer Line from Awi-9 to WPS 

Gn. Salak

SEGS 

Completed 
8

Geothermal Utilization for Direct Use, 8” dia. x 2865 m Heating Pipe Installation 

Rantau Dedap 

SERD

Completed
9 RDI 18" dia x 400 m Bypass Pipeline Installation  Rantau Dedap  SERD Completed